Construction site

Pinebush Well Connections
340 & 381 Pinebush Road
Cambridge, Ontario

The Region of Waterloo

CIMA+

$2.9M

Sept 2022- April 2024

Installed environmental protection measures (e.g., silt fencing, erosion control)
Implemented site safety protocols (signage, barriers, PPE requirements)
Mobilized and set up office trailer and temporary facilities
Performed overdrilling to properly decommission the old well
Safely removed old well components and sealed the well per regulations
Excavated and installed new underground piping connections within the site
Integrated piping with existing systems and new well infrastructure
Excavated and poured foundation for new well house
Framed and constructed building structure
Installed interior finishes, insulation, and weatherproofing
Installed new pumps, piping, and control valves
Upgraded electrical systems and panels in the water treatment facility
Graded and compacted base for access roads
Integrated new SCADA system for remote monitoring and control
Installed road base, asphalt, or gravel as per project specs
Excavated and graded swales for stormwater management
Planted grass or erosion control materials to stabilize swales
Excavated trenches and installed new watermain piping Pressure tested and disinfected piping before service
Cleaned and re-developed existing well casing and screens
Supplied and installed new submersible pump and associated equipment
Connected new well equipment to upgraded systems
Performed system testing and verification of mechanical/electrical systems
Calibrated SCADA and instrumentation
Completed start-up and commissioning of the entire water system.