Stevensville-Douglastown Lagoon Cell 2 Cleanout
CIMA+
$4.2M
July 2023 - October 2024
Site environmental control including silt fence and check dams. By-pass system implementation and dewatering of cell 1. Temporary aeration system installation and commissioning. Biosolid removal and disposal offsite using various methods. Review and assess the lagoon liner for faults, repair the liner as required. Excavation and benching/remediation of surrounding berm and berm liner. Demolition and disposal of existing aeration system. Supply and installation of permanent aeration system complete with commissioning. Install new baffle curtain. Site remediation including grading, topsoil, seed and site demobilization.